Total facility power 1,500 kW, IT equipment power 1,000 kW gives
PUE: 1.5 · DCiE: 66.7% · Overhead: 500 kW

Estimate only. Not engineering or safety advice. Check the result against the applicable standard and the equipment data, and have a competent engineer review it before it is relied on. Terms of use.

Open in the calculator with these values

About this calculator

This page calculates PUE, DCiE and overhead from total facility power and IT equipment power. Change any value or its unit and the result updates. The steps below show the working for the default values, so you can check each line against your own method.

Limits of this calculator

A single spot reading can mislead. Use energy over a full year so seasonal cooling load is included.

Cross-check: 6 reference cases, calculated from textbook formulas coded separately from the engine by the same author, agree with this calculator. This is not an independent review.

Verification status: Engineering reference

Engineering reference. Formula and method documented and tested against separately coded reference calculations. Not yet Verified: the evidence listed on this page is still needed.

What this calculator checks

What remains unverified

Verification register entry

Calculation authorRahul Sharma (author)
Technical reviewNo independent technical review has been carried out
Individual professional approvalNot recorded
Formula referencenot recorded
Standard and editionISO/IEC 30134-2, 2026 Ed 2
Standard review statePublic-scope screened; licensed clause review still pending
Scope-screening noteDefines data-centre PUE measurement, calculation and reporting. The calculator implements the basic total-facility-power / IT-equipment-power ratio; metering boundaries and reporting conditions must follow the standard.
Cross-check test cases6 reference vectors (tests/reference_vectors.json)
Review datenot recorded
Next review datenot recorded
StatusEngineering reference

Needed before this calculator can be marked Verified: reviewer name, qualification and review date; licensed clause-by-clause standard review; exact formula reference; formula source (textbook or standard); next review date.

Formula

PUE = total facility power / IT power DCiE = 1 / PUE × 100

Worked example

InputValue
Total facility power1,500 kW
IT equipment power1,000 kW
  1. PUE = 1,500 / 1,000 = 1.5
  2. DCiE = 100 / 1.5 = 66.67 %
  3. Overhead = 1,500 − 1,000 = 500 kW

Assumptions

A single spot reading can mislead. Use energy over a full year so seasonal cooling load is included.

Inputs and results

InputUnitAllowed or shownNote
Total facility powerkWgreater than 0 kW
IT equipment powerkWgreater than 0 kW
ResultUnitAllowed or shownNote
PUE(number)Shown to 2 decimal places
DCiE (IT share of total, %)(number)Shown to 1 decimal place
Overhead (cooling, losses, lighting)kWShown to 1 decimal place

How it is calculated

Each input is converted to the base unit of its quantity, the formula above is applied in the order shown in the worked example, and each result is shown in the unit you choose. Results are held at full precision and rounded only for display, except where a step selects a standard size, as the worked example shows. A value outside its allowed range is refused with a message instead of giving a result.

How the result changes with total facility power

Total facility power (kW)PUEDCiEOverhead (kW)
1,5001.566.7500
3,000333.32,000
6,000616.75,000
15,000156.714,000

Other inputs are the same as in the worked example above.

Standards and further reading

Lamp and luminaire data come from the manufacturer; the illuminance targets that apply come from your project specification and local regulation. These are named as background reading. Elecmetric does not embed clause text or rating tables, and the reviewer record for this calculator is separate from this list.

Frequently asked questions

What do I need to enter?

Enter total facility power and iT equipment power. Change the unit of a value with its selector and the result stays the same.

What does this calculator assume?

Both powers are averaged over the same period. IT power is measured at the PDU or rack outlet.

Which calculators should I use next?

Common next steps are Rack Heat Load and Airflow and UPS Battery Runtime. The related links at the bottom of this page open them.

How accurate are the results?

Every figure comes from the same tested engine as the Elecmetric calculators and is meant for estimating. 6 reference cases, calculated from textbook formulas coded separately from the engine by the same author, agree with this calculator. This is not an independent review. Check design values against the standard and the equipment data you work to.

Formula guides and reference

Longer explanations with worked examples and tables, written for the same topic.

More Lighting and Facilities calculatorsAll engineering calculatorsData Centre PUE in Elecmetric

Tell us how to improve this page

This opens your email app. Nothing is sent until you press send.